1. Loan Structure & Indicative Term Sheet
Because USDA REAP and utility efficiency programs operate strictly as post-commissioning reimbursements, commercial lenders will not advance against grant award letters without an explicit Grant Anticipation Note (GAN) or Specialty Equipment Bridge Facility.
| Term Sheet Parameter | Indicative Terms | Notes / Rationale |
|---|---|---|
| Facility Size | $800,000 | 100% of verified REAP ($500k) + DTE rebate ($300k) receivables. |
| Facility Type | Non-Revolving Equipment Delay Bridge Loan / GAN | Draw schedule tied to equipment delivery milestones. |
| Maturity / Tenor | 12 Months | Provides a 6-month buffer beyond the expected 6-month reimbursement cycle. |
| Pricing / Interest Rate | SOFR + 3.75% to 4.50% (or ~9.00% – 9.75% Fixed) | Reflects asset-backed short-term commercial exposure. |
| Repayment Structure | Interest-Only (I/O) Monthly, full balloon on maturity | Balloon is retired immediately upon disbursement of proceeds. |
| Prepayment Penalty | 0% / No penalty | Crucial: Must allow immediate payoff the moment DTE/USDA checks clear. |
| Origination Fee | 1.00% – 1.50% ($8,000 – $12,000) | Standard commercial bridge underwriting fee. |
| Primary Collateral | First-priority lien on qualifying lighting and HVAC equipment; collateral assignment of grant/rebate proceeds. | UCC-1 filing specifically on the financed equipment assets. |
2. Collateral Mechanics & Cash Waterfall Control
Lenders will underwrite this credit based on the certainty of the reimbursement receivable, not on the operational farm’s early revenue. To make the facility bankable, structure the control accounts as follows:
[USDA REAP / DTE Energy]
│
│ Direct Wire / Assigned Remittance
▼
┌─────────────────────────────────────────┐
│ Dedicated DACA Escrow Account │
│ (Deposit Account Control Agreement) │
└───────────────────┬─────────────────────┘
│
▼
┌─────────────────────────────────────────┐
│ 1. 100% Sweep to Bridge Principal │
│ 2. Settle Unpaid Accrued Interest │
│ 3. Release Surplus Equity to Operating │
└─────────────────────────────────────────┘
- Collateral Assignment of Grant Proceeds: The borrower signs a legal assignment transferring rights to the REAP disbursement and DTE rebate check directly to the lender.
- DACA / Restricted Inflow Account: Set up a blocked account governed by a Deposit Account Control Agreement (DACA). The formal banking instructions registered with USDA and DTE point directly to this account, preventing funds from mingling with general operating cash.
- Mandatory Cash Sweep: The credit agreement specifies that 100% of incoming grant/rebate funds are automatically applied to extinguish the bridge balance, followed by an immediate lien release.
3. Drawdown & Milestone Schedule
Bridge lenders do not release $800,000 on day one; funds are released against supplier invoices to ensure the asset value matches the drawn balance:
Month 0: Draw 1 ($350,000) ──► 50% deposit for LED & HVAC order
Month 2: Draw 2 ($350,000) ──► Equipment on-site & mechanical installation
Month 4: Draw 3 ($100,000) ──► Electrical connection & commissioning sign-off
Month 6–8: Payout Event ──► DTE inspection & USDA payment sweep → Loan Closes
- Tranche A ($350,000): Released upon presentation of firm equipment Purchase Orders (POs) from DLC-listed LED manufacturers and HVAC vendors.
- Tranche B ($350,000): Released upon physical delivery to the Michigan facility and installation by a licensed MEP contractor (verified by site inspection / bill of lading).
- Tranche C ($100,000): Released upon final mechanical commissioning and submission of the formal post-installation verification packages to DTE and USDA.
4. Financing Cost & Cash Outlay Model
Assuming an average outstanding balance of $600,000 over a 7-month actual duration at a 9.25% annual interest rate:
All figures in USD.
- Origination Fee (1.25% of $800,000): $10,000
- Lender Legal & Documentation Fee: $4,500
- Third-Party Site Inspection / Verification Fee: $2,000
- Accrued Interest (Avg. $600k @ 9.25% for 7 months): $32,375
- Total Carrying Cost of Bridge Facility: ~$48,875
- USDA REAP Obligation of Funds Letter: Formal notification (Form RD 1942-46 or equivalent Letter of Conditions) confirming the grant has been awarded, funds are federalized/obligated, and the payout is solely contingent on completed installation.
- DTE Pre-Approval Voucher: A signed pre-approval confirmation from DTE Energy’s C&I Energy Efficiency Program guaranteeing the rebate reservation based on the approved engineering energy model.
- PE-Stamped Commissioning Requirement: A covenant requiring a certified Michigan Professional Engineer (PE) to inspect and sign off on fixture counts, baseline kW offsets, and operational run hours.
- Sponsor Backstop / Limited Guaranty: A personal or corporate completion guaranty ensuring that if the installation fails verification due to construction errors, the sponsors will fund the principal shortfall directly.